|
A breif Overview
Hooghly River is the main source of potable surface water
for the city of Kolkata supplied from the age-old Palta Water
Works now rechristened as Indira Gandhi Water Treatment Plant.
The Palta Water Works ,spreading over a sprawling strechh
of 480 acres,was the first intake point constructed during
1864-1870 for generation and supply of water . Initiated with
a humble capacity of 6 mgd (million gallon per day),filtered
water was generated through sedimentation in pre and final
settling tanks and slow sand filteration in the Old Series
of 12 filter beds. Further addition of 24 beds with a capacity
of 1 mgd per bed,was made during the period 1888-1893. In
1905,filter beds with 2 mgd capacity ,called New Series was
started . Further addition took place in between 1920 and
1936 when 17 nos.of 3mgd capacity and 1 no.of 2mgd capacity
filter beds,called Extension Series were introduced.
It is said that old is gold and the relentless service of
this age-old pumping station is certainly proving the point.
With an output of 130 mgd,the plant seems to have perenial
capacity to serve.
The slow sand filternation system is an effective and reliable
system which does not required daily washing. A single bed
can work upto 100 to 120 days.Formation of a biological mat
soon after effective charging removes turbidity,colour and
microoraganisms,by 95%. Due to this process,requirement of
chlorine as a disinfectant of about 10 to 20 mm of top sand
layerr every 100 day,make the bed ready for reuse.
Further development took place with the introduction of rapid
gravity filter with 12 beds and 20 mgd capacity during 1952.
This process helped in reducing the sedimentation time. In
1968,another 60 mgd rapid gravity filteration unit was added.
The present arrangement did not however,seem to suffice the
demand level. In 2002,KMC supplied 281 mgd of water,falling
short of the demand by almost 50 mgd. However,in 2003,the
average supply rose to 334 mgd, meeting nearly 90% of requirement.
Keeping in tune with the growing rate of population and proportionally
accelerating rate of demand,KMC has undertaken several capacity
enhancement and upgradation programmes and hopes to exceed
the demand by 2005.
New Palta Water Wokrs at Indira Gandhi Water Treatment Plant,is
a notable step in this development process. It is a 100 mgd
water generation project. This scheme,which is to be commissioned
on 29th July 2004,further augments the capacity of Palta by
60 mgd,taking the already commissioned 20 mgd treatment plant,out
of the planned 100 mgd additional supply. This ,along with
the increased supply from Garden Reach Water Works,will increase
the per capita water supply to 234 liters per day from the
present 202 liters per day. This would indeed be a feather
in the cap of KMC,as it benchmarks the highest water supply
level in the country.
| Kolkata: Water Supply Statistics at a
Glance |
| Total daily potable water
supply (in million litre) |
1350 |
| Per capita availability of water per day
(in litre) |
202 |
No. of Tube Wells Big daimeter
Small Diameter |
455
7875 |
No. of connections Domestic
Industrial and Commercial |
2,12,000
25,000 |
Public Access Standard Posts (in nos.)
Unfiltered water through street hydrants (in nos.) |
17,019
2000 |
| No. of reservoirs Present |
7 |
Under construction
Combined capacity (in million gallon) |
14
96 |
| After Commissioning of New Palta Per Capita
Water Availability will be 234 Liters Per Day |
Intake Jetty
New Palta is a completely self-sustained water treatment
plant capable of suplying 100 million gallon water per day.
In addition to the two old jetties,it has a new jetty to draw
unpurifed river for treatment. The delivery process is aided
by three 72" suction mains,that end in underwater bellmouths.
Intake Pumping Station
The intake pumping is equipped with six pumps of 42 mgd capacity
,each having motor units. The intake station has 100% standby
capacity. Collectively,only 3 pump- motor stes are capable
of drawing 100mgd water from the river. The pumping station
,equipped with modern state-of-the-art control pumps,controls
all the operations of the pumps. The impure water extracted
from the river consits of suspended purification.
| Equipment |
Nos |
Capacity of each |
Manufacturer |
| Pump |
6 |
1.75 mgh* 42mgd |
Mather & Platt |
| Motor |
6 |
6 KV/640 KW |
BHEL |
| Switch Gear |
1 |
6KV 10 Panel |
Bicco |
*mgh : million gallon per hour
Treatment Plant
The treatment plant is equipped with five modules eachh of
capacity 20 mgd for the purification of the 100 mgd intake.
Out of these five,three have already been constructed and
will commence operation from the day of inauguration. Built
with modern French technology of pulsator clarifier,the treatment
modules treat water through a sludge blanket created through
upward flow of alum mixed water. The five modules around the
central administrative building resemble the design of a fan.
The construction of two remaining modules will be completed
by 2005.
Pulsator Clarifier
This is a reactor type clarifier having inflow of water through
bottom. While allowed to get through the bottom,it gets thoroughly
mixed up with induced alum solution and chlorine gas. Moreover
the sludge formed out of coagulation is also getting a boost
for floating due to upward pressure. The sludge floating scatteredly
forms a thick blanket and floats little below the clarified
water face at 5. When this blanket is thick , it is supported
through supplemented thrust of pulsator plates at 4. When
it is furtehr thicker it spills through the drain at 10. Thus
raw coagulated and disinfected water passes throough the sludge
blanket field and clarified water is collected through the
gutters at 2 fro passing it to filter. The turbidity of the
clarified water achieved in this process is below 10 NTU.
Pressure Station
The water purified at the treatment plant,needs to be trasmitted
to the city at a distance of almost 40 km. To precisely conduct
the task,a new pressure station equipped with six pump-motor
sets has been constructed. While three of these pumps are
sufficient to create the pressure for transmission of 100
mgd water, the remaining three provides 100% standby for any
emergency situation is powerful enough to create a water jet
of 110 feet height,equal to that of a ten-storied building.
| Equipment |
Nos |
Capacity of each |
Manufacturer |
| Pump |
6 |
36 million gallon per day |
Kriloskar Brothers Ltd. |
| Motor |
6 |
6 KV/875 KW |
Lawrence Scott(UK) |
| Switch Gear |
1 |
6KV 13 Panel |
Bicco |
| Transformer |
|
6KV/440V250 KVA |
Eastern Engineering Equipment |
Pipeline
62" HDPE pipes,extending for 3.5 km have been laid down
to carry the entire capacity of 100 mgd water from Palta to
Tallah. The diameter of existing pipelines were 48",54"
,60" and 72". KMC ,for the first time in India,rehabiliated
the one km 62" corroded HDPE ( High Density Poly Ethylene)
pipes. With the help of this new technology,the completion
of work was possible within a record time of 29 days, without
disrupting traffic or damaging the roads.
Electrical Sub-station
One 33 KV electrical sub-station has been commissioned to
receive the direct high tension power from CESC source for
the augmented electricel installations including existing
electrical installations. Another 6KV electrical sub-station
with necessary network has been commissioned to step down
th ehigh tension dedicated servial to suit the input requirement
of all new existing electrical prime movres and other ancillaries.
| Equipment |
Nos |
Capacity of each |
Manufacturer |
| Transformer |
2 |
33KV/6KV 15 MVA |
Alstom |
| Transformer |
1 |
6KV/4KV 500 KVA |
Alstom |
| Switch Gear |
1 |
33KV 5Panel |
Siemens |
| Switch Gear |
1 |
6KV 10 Panel |
Siemens |
| Switch Gear |
1 |
6KV 13 Panel |
GEC Alstom |
Future Treatment Plant
While 60 mgd treatment facility has been commissioned,work
has already started for construction of another 49 mgd treatment
plant.
This treatment plant would be built on Settler Technology.
This will imply that the entire Palta facility would be a
mix of old and reliable,maintenance free slow sand filter,more
advanced rapid gravity filter,state-of-the-art pulsator and
relatively low O&M based plate Settler Technology.
The 40 mgd treatment plant is planned to get ready by April
2005.
Also in order to improve the availability and quality of
water supply in the city ,construction of water treatment
plants at Jorabagan and Watgunj has been undertaken.
Watgunj
This 5mgd water treatment plant cum booster pumping station
is being constructed with the aid of new technology at Watgunj
Square to supply water from Palta Water Works and meet the
requirement of filtered water for th eresidents of Watgunj
and Hastings area.
Jorabagan
This 8mgd water treatment plant and 3.5 mgd underground reservoir
cum booster pumping station will filter and supply water generated
at Mullick Ghat Pumping Station to the water scare area of
Chitpur,Nimtala,Sovabazar and adjoining areas of North Kolkata.
Reservoir and Booster Pumping in Offing
Bagmari
This 6mgd underground reservoir cum booster pumping station
,which is to be commissioned in August ,is one of the largest
boosting sations in the city. With a total of 29.36 km of
distribution line,it shall supply water from Palta Water Works
to the residents of Maniktala,Ultadanga,Bagmari and adjoining
areas thus substantially reducing the dependence on ground
water in these areas.
Ranikuthi
This 3.5 mgd underground reservoir cum booster pumping station
is ready to serve the residents of Tollygunge,Dhakuria and
adjoining areas. Located by the side of Ranidighi in Tollygunge,this
station would supply filtered water of Garden Reach Water
Works through an elaborate distribution pipeline network.
Kasba
This 3.5 mgd underground reservoir cum booster pumping station
,which is to be commissioned by the end of this year,will
get water from Palta. The citizens of the fast growing area
of East Kolkata shall be receiving treated water from this
booster station. This will also substantially reduce the dependence
on ground water in these areas.
Kalighat
This 4 mgd underground reservoir cum booster pumping station
is being constructed at Kalighat Park to supply water to a
vast area of South Kolkata. The dedicated supply line to bring
water from Garden Reach Water Works is beign laid down to
meet the completion deadline of the project of 31st december
2004.
|